Split the unit price into the part that genuinely tracks the resin index and the part that does not, then index only the first. On a moulded part that is the granulate. Machine time, labour, packaging and freight follow their own cost drivers, and the tool is either already paid for or amortised at a fixed amount per part. Fix the conversion side for an agreed period, tie the material side to one named public quote with a dead band and a fixed review date, and handle currency as a separate clause. You then negotiate a mechanism once instead of a number every quarter.
This is about how such an agreement is built and which mechanisms exist. What is enforceable in any particular jurisdiction is a question for your own lawyer.
How much of your unit price actually tracks the resin index?
Far less than the headline on a price increase letter suggests. A moulded unit price is built from granulate including runner loss, machine time with energy, labour and handling, any secondary operations such as printing or assembly, packaging, freight and margin. Only the first line follows the resin quote. If granulate goes up 20%, your unit price goes up by 20% times the material share, and no more.
How big that share is depends on the part. A thick walled part with a short cycle is material heavy. A small part with a long cycle, a side action and a manual step at the press is machine heavy, and there a resin rise does relatively little.
| Worked example, invented unit price of €1.00 | Thick walled part, short cycle | Small part, long cycle, with side action | | --- | --- | --- | | Granulate including runner loss | €0.60 | €0.25 | | Machine time and energy | €0.20 | €0.50 | | Labour, secondary operations, packaging | €0.12 | €0.17 | | Margin | €0.08 | €0.08 | | Unit price after a 20% resin increase | €1.12 | €1.05 |
The same resin move produces 12% on one part and 5% on the other. The figures are invented to show the arithmetic, but the mechanism is real: ask for the material share per part number when the contract starts, and record it. Without that number, every later indexation is an assumption.
How do you build an indexation clause that is not a quarterly negotiation?
By making six things explicit: the reference, the baseline, the scope, the dead band, the interval and the burden of proof. Leave one out and every review turns back into a conversation.
- Reference. One named publication, with region and delivery terms. A polymer quote sits closest to your granulate; a monomer quote moves harder and needs an agreed pass-through factor.
- Baseline. The index level on a named date, with the unit price that belongs to it. Without a baseline there is nothing to measure against.
- Scope. Which percentage of the unit price moves, fixed at the start rather than reopened at every review.
- Dead band. A range in which nothing happens, for example a move of less than 5% against the baseline.
- Interval. A fixed moment, quarterly for instance, with a notice period.
- Proof and symmetry. The manufacturer supplies the index level, in both directions.
The dead band and the interval are not formalities. The European monthly contract price for propylene, the feedstock under polypropylene, settled at €1,000 per tonne in March 2026, €1,555 in June and €1,365 in July: a fall of €190, roughly 12%, in a single month. With no dead band and no interval you would have repriced three times in five months, and the July review would have undone the June one. On a quarterly rhythm with a 5% band, the same movement becomes one correction.
Mind the gap between the monomer quote and what you actually pay, too. Your manufacturer buys a compound with additives, colour and often a filler, and that price follows the monomer with damping and a lag. If you do link to a monomer, agree a factor, say 70% of the index movement, and put the factor in the contract instead of arguing it every quarter.
How long does a unit price realistically hold?
Between three and twelve months, and the length is something you buy. The longer the price is fixed, the more risk the manufacturer carries, and that risk sits in the number as a buffer. A six month price is not a free upgrade on a three month price.
What sets the term is how your manufacturer buys resin. If he buys on a monthly contract, a quarterly price is the natural fit. If he buys a batch for your part number, validity really runs until that batch is used up. Ask the question and tie validity to his purchasing moment rather than to your financial year. That single question moves the conversation from negotiation to arithmetic.
Keep two lines out of the discussion entirely. Tooling amortisation, where it sits inside the piece price, is a fixed amount per part and does not belong in the index. Freight and packaging have their own drivers and belong in their own line, so a fuel surcharge does not arrive through the material clause.
Which currency do you contract in, and who carries the risk?
Whoever can hedge it most cheaply, and that is a decision rather than a default. The scale is real: the euro to dollar rate in 2026 moved between roughly 1.21 in late January and roughly 1.13 in late June, about 6% between the extremes, with publications differing slightly. That is more than most manufacturers take out of a process in productivity over a year.
| Arrangement | Who carries the risk | What it costs | When it fits | | --- | --- | --- | --- | | Price in your own currency | The manufacturer | A buffer you never see itemised | Smaller volumes, you want one number in your costing | | Price in the manufacturer's currency | You | The cost of your own hedge | You have a bank or treasury that books forwards | | One currency with a currency clause | Shared | Administration and an explanation at every review | Longer contracts and larger volumes |
A currency clause is built like the material clause with a different variable: one named reference rate, a baseline rate with a date, a band in which nothing happens, a fixed review moment and symmetry in both directions. Look at which part of the unit price is genuinely exposed. If the granulate is bought in dollars while labour is paid locally, only that first part should move. A clause that swings the whole unit price with the rate transfers more risk than actually exists.
What happens to the price if you order below the agreed volume?
The tier that matches your actual offtake applies, and that is exactly the arrangement to settle before you need it. Tiers per order are simple but expensive as soon as you reorder. Tiers per year with a true-up are cheaper on spread demand, but produce a back-charge if you stay under the threshold.
A worked example on invented figures, using index points rather than currency. Say 10,000 parts sit at index 100, 25,000 at 96 and 50,000 at 92. You commit to 50,000 and take 30,000. The question is not only which tier applies, but over which parts it is recalculated and when it is settled. Write down both.
Three further mechanisms cause more friction than the price itself. A rolling forecast with a fixed window, for instance four weeks firm, eight weeks flexible and twelve weeks indicative, makes visible what your manufacturer is buying against. A changeover surcharge on a small repeat order is reasonable as long as you know how it is calculated. And where the tool is amortised per part, a lower offtake simply means the tool is not paid off, so agree what happens then. That ties straight into who owns the tool, which is the subject of our piece on mould ownership when you switch manufacturer.
Finally, pin down the build-up rather than only the bottom line. Always ask for the tool price and the unit price together, as we set out in our piece on comparing mould quotes over the programme, and ask for cycle time and material share behind every unit price. For the other levers beside the pricing agreement, see our piece on reducing manufacturing costs on an existing product. And if the region you produce in changes, your currency position changes with it, which is part of what we cover in moving production out of China. How a route from tooling to series runs with us, including the signed mould property contract before production starts, is set out in our process.
Production Heroes takes products from design to series production, from feasibility and cost price to sourcing and supply chain, and supplies moulds and tooling to manufacturers across Europe, from the Netherlands and its own presence in China.
Sources: the European monthly contract settlements for propylene in 2026 (March €1,000 per tonne, June €1,555, July €1,365) come from public reporting on the monthly FD Northwest Europe settlements, among them OPIS (March 2026) and Polymerupdate (June and July 2026); publications differ by a few euros per tonne. The 2026 euro to dollar levels come from the annual overviews published by Pound Sterling Live and ValutaFX (2026), which put the high near 1.21 in January and the low near 1.13 in June and differ slightly from each other. The worked examples in the text and in the FAQ use invented assumptions and are not a quotation.
Frequently asked questions
- Which index do you use when your compound has no published quote?
- Link to the nearest published polymer or monomer quote and agree a pass-through factor, for example 70% of the index movement. Name the publication, the region and the delivery terms, because the same polymer carries a different number in every publication.
- Does an indexation clause have to work downwards too?
- Yes, and write it that way. A clause that only moves up is a delayed price increase. Use the same dead band and the same interval in both directions, and make it the manufacturer's duty to supply the index level even when it has fallen.
- Should tooling amortisation in the piece price be indexed?
- No. A mould is either paid once or amortised at a fixed amount per part, and it does not move with resin. Without that exclusion you are indexing a cost that is already fixed. Keep freight and packaging in separate lines too; they have their own drivers.
- What do you ask for to verify a price increase?
- The index level on the baseline date and on the review date, from the agreed publication, plus the material share of the unit price as recorded when the contract started. Those three numbers let you recalculate it yourself. A supplier letter with no index print is not evidence.
- How much notice should a price change carry?
- Tie the notice period to your own order horizon so open orders keep the old price. Also agree that the price valid on the order date holds through to delivery, or a change quietly reaches stock that has already been produced.
- Do volume tiers apply per order or per year?
- That is the point to settle up front. Per order is simple but expensive on repeat orders. Per year with a true-up is cheaper on spread demand, but produces a back-charge if you fall below the tier. Agree who calculates that true-up as well.